Beacon Electric completed the Mane Everest project in Lebanon, Ohio in only 6 months.
The MANE Everest project contract was valued at two million dollars closely followed by the US Headquarters which was completed 5 months later with another two million dollar electrical contract.
The Everest Project included all stainless steel piping, tray and supports. The work included distribution, branch power and lighting, controls and work associated with production lines.
Beacon’s electricians worked in concert with MANE’s technicians from France as each line was installed. At various times Beacon’s manpower exceeded thirty electricians and six supervisors working 12 hour shifts to meet critical deadlines for the installation of sophisticated equipment brought in from over-seas. Adapting to various voltages and configurations was an ongoing problem that the whole team saved to complete the Everest Project on time.